The project required the design and construction supervision for the expansion of the existing refractories plant for the manufacture of monolithics products. Significant features include the installation of materials conveyors, dust collectors, skip hoist, bucket elevators, bar screen, chute hood, and duct with a control room for the computerized operation of the plant.
TCGI was involved in feasibility studies, detailed engineering design and construction supervision.
Tupperware Manufacturing Plant
Location: Laguna, Luzon Philippines
Client: DART Philippines, Inc.
Funding Agency: Private
A manufacturing plant totaling 26,000 sq.m.of floor area, the project consists of powder preparation, molding, quality control and warehousing facilities, including utility supports like power, water and waste water treatment plants.
TCGI provided detailed engineering design and construction management services.
Ferrochrome Plant
Location: Cagayan de Oro City Mindanao Phil.
Client: Ferrochrome Philippines, Inc.
Funding Agency: Private
The project is a 50,000 MT/year ferrochrome smelter plant complex located on a 20-hectare lot. The complex contains process structures; raw materials and finished product storage; bunker fuel and gasoline tanks; a power substation; and staff houses.
TCGI conducted a comprehensive feasibility study and provided detailed engineering design and construction supervision services.
Semirara Coal Mining Facilities
Location: Semirara Island, Antique Visayas, Philippines
Client: Semirara Coal Corporation
Funding Agency: Private
The project is a 50,000 MT/year ferrochrome smelter plant complex located on a 20-hectare lot. The complex contains process structures; raw materials and finished product storage; bunker fuel and gasoline tanks; a power substation; and staff houses.
TCGI conducted a comprehensive feasibility study and provided detailed engineering design and construction supervision services.
3 Salcedo Place Condominium
Location: Salcedo Village, Makati City
Client: Ayala Land, Inc.
Funding Agency: Private
A condominium of two towers (A and B) resting on a four-storey podium, and four levels of basement parking. The total enclosed built-up area is approximately 57,000 sq.m. exclusive of the basement parking. Tower A with 25-storey and Tower B with 30-storey are both for residential uses.
TCGI provided construction management services including progress monitoring, technical assistance and project post-evaluation.
Asia Tower
Location: Cagayan de Oro City Mindanao Phil.
Client: Ferrochrome Philippines, Inc.
Funding Agency: Private
A 26-storey office residential condominium located beside the Asian Institute of Management, and is accessible to the various commercial and office buildings in Makati. The ground and 2nd floors are designated as office spaces, while the 5th up to the 24th floors have typical residential units. Special units (loft type) are available from levels 19 to 24.
TCGI provided construction management services.